The Office of Public Works will this morning defend the ballooning cost of modular homes provided for people fleeing the war in Ukraine.
Last month it emerged that the cost of the units had more than doubled compared to original estimates, and now stands at €442,000.
In a report in September, the Comptroller and Auditor General (C&AG) found that the total cost for the project of providing 654 homes will be in the region of €289.3 million
In an opening statement given to members of the Public Accounts Committee (PAC), which is due to hear from the OPW today, officials from the State body argue that the cost is higher than forecast because of the emergency nature of the pilot programme.
Gardaí search for potential information left behind by deceased Kyran Durnin murder suspect
Enoch Burke’s father Sean jailed for courtroom assault on garda
We’re heading for the second biggest fiscal disaster in the history of the State
Housing in Ireland is among the most expensive and most affordable in the EU. How does that happen?
It also outlines issues such as “complications around sites, access issues and utility connections”.
It argues that the C&AG found that the cost of the programme was equivalent to providing hotel rooms for 2,640 Ukrainians for five years, but the modular homes will have a 60 year lifespan and can be used for social housing in the future.
“By any assessment it is better to have this new State asset, than to be renting hotel rooms for five years. This State asset will be available for another 55 years,” the committee will be told.
The OPW also pointed out that families were accommodated at 10 sites within 13 months, a relatively short timeline for housing delivery.
“An assessment on delivery of this project will begin shortly and will consider all of the factors,” the committee will be told, while the OPW will also defend the €1.4 million spend on a security hut at Government Buildings. It will say that while awaiting a decision on the conversion of a reading room in Leinster House into a second chamber or committee room, it is not taking any further action at this time.
The OPW will also outline steps taken in the wake of the Leinster House bike shed saga, including an independent audit of the project, and measures to strengthen value for money on future projects.
The OPW will also be asked about flood relief schemes – 55 of which have been completed while 100 others are under way nationwide.
The Committee is due to meet at 11am and will be chaired by its deputy chair, Social Democrats TD Catherine Murphy, as Sinn Féin moves to replace its former TD Brian Stanley who led the committee during this Dáil.
- Sign up for push alerts and have the best news, analysis and comment delivered directly to your phone
- Join The Irish Times on WhatsApp and stay up to date
- Listen to our Inside Politics podcast for the best political chat and analysis