Heads should roll at Irish Rail
There must be repercussions for writing off €50 million of taxpayers’ money
There must be repercussions for writing off €50 million of taxpayers’ money
New train traffic management system will need to be put in place, says Irish Rail, without providing estimated cost
NTA accepts move by Irish Rail to terminate contract with IT contractor Indra but warns of ‘significant financial consequences’
NTA privately warns Irish Rail of ‘significant financial consequences’ arising from move to fire IT company Indra
Poking fun at the Cork hurlers’ misfortune might come better from a group less prone to service hiccups
Train operator argues mast is 130m from old Cahir station and it has constructed 700 masts around State without complaint
Project has experienced considerable delays and budget overruns, Oireachtas transport committee hears
Lessons can and must be learned from Irish Rail and other State bodies’ failings
Authority also expected to tell Oireachtas committee demand is exceeding supply on public transport
On current projections, it will have taken 27 years to reopen about 150km of railway
About €30m has been spent on project, but final decision will fall to National Transport Authority
Darragh O’Brien says new traffic management system is needed, but he is far from happy about how project has been delivered
Up to 20,000 rail users in north Dublin severely disrupted after damage to overhead lines
‘Passengers became visibly lethargic’ as carriage overheated during record temperatures, a reader says
Education spending, electric bus fleet and Children’s Sciene Museum among issues rounded on by committee
Early Edition with Andrew McNair
Company asked why millions continued to be spent on management system despite long existing concerns
TDs to hear from State-owned rail company about €50m write-down on system to manage movement of trains
Just two spare central processing units remain for system that was meant to be replaced in 2024
Oireachtas committees to begin investigations into cost overruns on project once called the ‘brain of the railway’ by a Government Minister
Initial testing has ‘revealed problems’ with latest software delivered by contractor
Roll-out of new carriages is delayed, but company says this has nothing to do with their size
Despite multiple large events this weekend – Women’s Mini Marathon, Forbidden Fruit and Bloom Festival – Dart disruptions are still expected
Everything you need to know about the band’s concert on Friday, May 29th
Scathing criticism at Dáil committee follows report saying State-owned train operator has no confidence in traffic management system
State-owned rail company does not have confidence the system to control train movement can be deployed on the network
Journey from Navan to Dublin expected to take no more than 60 minutes under latest plans
Key IT projects at Government departments and State agencies set to run €61m over budget
Irish Rail services were curtailed twice by blaze near between Bray and Greystones
Stadler trains, due in 2028, will have spacious dining areas and unaided boarding on exterior doors
Six-month construction project comes alongside fast-tracked building of Adare bypass in time for golf event
Close partnership is of benefit to all parties concerned
Minister for Transport Darragh O’Brien expresses ‘dissatisfaction at the rate of progress’ on project
Crosswords & puzzles to keep you challenged and entertained
How does a post-Brexit world shape the identity and relationship of these islands
Read the digital edition of The Gloss magazine now
Weddings, Births, Deaths and other family notices